Construction

Manufacturing & Installing 66 Guy Wires At Salisbury District Hospital

A 30-metre chimney in a working hospital had to come down, and the scaffold tower around it could not stand without the 66 guy wires we made, fitted and tensioned.

Client Confidential
Service Bespoke Guy Wire Manufacture & Installation
Location Salisbury District Hospital

Background

A new client came to us about a job at Salisbury District Hospital. A 30-metre chimney had to come down, and because it stood centrally between the hospital buildings, getting to it was the first problem.

The plan was to build a scaffold tower around the chimney, giving a safe working platform to dismantle and remove it from.

Initially, we were asked to quote for 54 guy-wire ropes, all associated equipment, and the full installation of the guy-wire system holding the scaffold up.

SWL Guy Wire Case Study

The Challenge

The design drawings named every individual guy wire, the anchor it ran to, and the exact tension load it had to be set at. With 54 wires to manufacture, identify and keep track of, there was no room to get one wrong.

Where the tower stood made it harder again. The wires had to pass through various sections of roof cladding on the surrounding hospital buildings and into the roof spaces, where the ground anchors sat.

Partway through, the designers raised the count from 54 to 66. That meant another 12 wire rope assemblies and the equipment to go with them, manufactured and supplied at very short notice.

The main contractor’s programme also changed several times, so we rearranged planned attendance at short notice and worked weekends to keep the job on schedule.

Hospital Chimney Guy Wire Installation

The Solution

We manufactured each assembly to the specifications on the design drawings and prepared it for its own position on the structure.

Our engineers worked alongside the client, the scaffold contractor and the project team, fitting wires as each stage of the scaffold became available. The wires ran through the designated sections of roof cladding and onto the specified anchors inside the roof spaces.

Because every wire had its own tension requirement, this was never a case of connecting them and tightening them up. We tensioned each one progressively to its specified load and used our QuickCheck tension meter to measure and confirm what had actually been applied, so we could show that every wire matched the design.

We came back the following week to check them and confirm they were still holding their specified loads as the scaffold structure progressed.

Guy Wire Supply At Hospital

The Result

Delays in scaffold erection meant we couldn’t finish until the scaffolders built the final stage of the tower. However, as soon as it was ready, we put a four-man team on site and completed the remaining installation and tensioning without holding anything up further.

All 66 wires went in at their correct locations, tensioned to their individually specified loads and verified with calibrated measuring equipment. With the system complete, the scaffold was ready, and the crane could come onto site to start taking the 30-metre chimney down, much to the relief of the customer and the wider project team.

What started as 54 guy wires finished as 66 individually specified assemblies, every one manufactured, installed and tension-checked by us.

SWL Chimney Removal Case Study