With lifting from above ruled out, the only realistic way to do it was to bring all sixteen bridges down to one end of the long-travel rails and work from there. Getting them there took time in itself, because each crane’s anti-collision system had to be safely overridden before it would move.
With the bridges parked up, we decommissioned and isolated the 300-amp power supply, then took the hoists and ancillary equipment off each one to bring the weights down to something we could handle.
From there, we worked our way back along the rails, lifting out each section with two 7.5-tonne forklift trucks in a controlled tandem lift. Tandem lifting on forklifts isn’t something we take lightly, so the whole thing ran off a detailed lift plan with a clean, well-managed area to work in, and that’s what let us get through more than thirty lifts without a single one going wrong.
Then came the bridges. Same two forklifts, same carefully worked-out sequence, and all sixteen came out without incident and without so much as a scratch to the paintwork.