Industrial

Supplying & Installing 175 Bays Of Racking On The Isle Of Wight

175 bays of racking had to go up a mezzanine floor on the Isle of Wight, and when the job ran four days over we covered the difference ourselves.

Client Confidential
Service Industrial Racking Supply & Installation
Location Isle of Wight

Background

A longstanding client asked us to quote for the supply and installation of 175 bays of industrial racking at one of their facilities on the Isle of Wight. The racking was for storing light goods only, and it all had to be built and positioned on a mezzanine floor to suit how the customer wanted the space to work.

That last point shaped the whole job. We had to get every component up to the mezzanine before we could assemble a single bay, and 175 bays is a substantial amount of material to move. We had to plan the delivery logistics and access into the work area well before anyone picked up a tool.

Background

The Challenge

Getting the racking to site came first, and we had to coordinate an articulated lorry delivery with our team attending the same day. Due to the island’s location, this made it harder to line up than a mainland delivery would have been.

Once it arrived, every component had to go up to the mezzanine floor. Moving the materials for 175 bays into the installation area was a considerable job on its own, and it took the team a significant amount of time before any assembly could start.

Then there was the space itself. The installation area was unventilated, and the heat and limited fresh air made the work demanding for the whole time the team were on site.

Racking Components Moved To Mezzanine Floor

The Solution

We arranged for the articulated lorry to deliver the racking to coincide with our visit. Once on site, our three-man team moved the components up to the mezzanine and began building and positioning the bays to the customer’s requirements.

The team worked through the initial seven days to push the installation on, but between the conditions and the time it took to move materials into position, seven days was not going to be enough. Rather than leave the job partially finished or rush the end, we extended the installation by four days at no extra cost to the customer.

With the bays erected and positioned, we fixed a label to each one showing its maximum load and identification number, so anyone using the racking can see what that bay is rated to take without having to find a drawing. On racking built onto a mezzanine, where the load limits of the mezzanine floor matter as much as the limits of the bays themselves, that marking is worth having in place from day one. We issued the customer certification upon completion.

Engineer Building Industrial Racking Bays On Site

The Result

All 175 bays went in at their required positions, giving the customer the storage arrangement they had asked for on the mezzanine and the capacity to hold the light goods it was specified for.

Between the load labels and the certification, they also came away with a clear record of what every bay in the facility is rated to carry. That record is where a racking inspection regime starts, because racking takes knocks from daily handling and needs periodic checks against the loads it was signed off for.

The Result